The results of drilling in the region of Muara Bakau generate a lot of mercury, so need to add filtering facilities.

Projects deep water in Jangkrik Field and Jangkrik North East at Muara Bakau undertaken by ENI Indonesia Limited require additional investment for procurement of mercury filtration (mercury removal) facilities of gas produced.

Mercury filtration facility investment worth U.S. $ 15 million. With the additional labor costs and so on, additional capex to be approximately U.S. $ 40 million.

Capital Expenditure (Capex) project was increased by about 17%.

On the other hand, operational expenditure (Opex) of the company has decreased because there were some things that were removed from the original plan because it is not needed.

So additional capex investment coupled opex decrease, no effect on the plan of development (PoD).

ENI had planned to drill 11 development wells offshore in the Muara Bakau.

Projects worth U.S. $ 4.13 billion, is expected to start production in 2017, and may contribute up to U.S. $ 5 billion on state revenues.

ENI  investments in Indonesia

Over the past four years, ENI claims to have discovered oil reserves of about 200 million barrels.

“In 2016, we will start producing 100 thousand barrels of oil per day,” said Managing Director of ENI Indonesia Ltd.., Carlo Vito Russo. (TEMPO.CO / April 14, 2013)

ENI predicts that the total investments made in Indonesia will provide ENI turning a profit in 2020. Because, production of which has been explored several blocks can only be enjoyed in 2016.

—— in Bahasa Indoensia ——-

Hasil pengeboran di wilayah kerja Muara Bakau menghasilkan banyak merkuri, sehingga perlu menambah fasilitas penyaringannya.

Proyek laut dalam Lapangan Jangkrik dan Jangkrik North East di Wilayah Kerja Muara Bakau yang dilaksanakan oleh ENI Indonesia Limited memerlukan investasi tambahan untuk pengadaan fasilitas penyaringan merkuri dari gas yang diproduksi.

Investasi fasilitas penyaringan merkuri senilai US$15 juta. Dengan tambahan biaya pekerja dan sebagainya, capex tambahan menjadi sekitar US$40 juta.

Capital Expenditure (Capex) proyek ini naik sekitar 17%.

Di sisi lain, operational expenditure (opex) perusahaan mengalami penurunan karena ada beberapa hal yang dihapus dari rencana semula karena dianggap tidak diperlukan.

Sehingga tambahan investasi capex yang dibarengi penurunan opex, tidak berpengaruh pada rencana pengembangan atau plan of development (PoD).

ENI sebelumnya berencana melakukan pengeboran 11 sumur pengembangan lepas pantai di Muara Bakau.

Proyek senilai US$4,13 miliar itu diharapkan dapat berproduksi mulai 2017, dan dapat berkontribusi hingga US$5 miliat pada pendapatan negara.

Investasi ENI di Indonesia

Selama empat tahun terakhir, ENI mengklaim telah menemukan cadangan minyak sekitar 200 juta barel.

“Pada 2016, kami akan mulai memproduksi 100 ribu barel minyak per hari,” ujar Managing Director ENI Indonesia Ltd., Carlo Vito Russo. (TEMPO.CO / 14 Apr 2013)

ENI memprediksi bahwa total investasi yang telah ditanamkan di Indonesia akan memberikan ENI keuntungan balik pada 2020. Karena, produksi dari beberapa blok yang sudah dieksplorasi baru bisa dinikmati pada 2016.

Related links:

References / read more:

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s