Jacket Construction of Oil & Gas Platform

jacket of Oil and Gas Platforms

“Project Quality Management System on Jacket Construction of Oil and Gas Platform”

Here, Author would like to share about why, what and how to establish, implement, document, and maintain the Project Quality Management System on Construction Work of Jackets, as part of Wellhead Platform EPCI Project Contract for Onshore / Offshore Oil and Gas Field Development.

WHAT IS JACKET OF OIL AND GAS PLATFORM ?

There are several types of oil and gas platforms and drilling rigs in offshore fields. (see Picture-1, there are: 1, 2) conventional fixed platforms; 3) compliant tower; 4, 5) vertically moored tension leg and mini-tension leg platform; 6) Spar ; 7,8) Semi-submersibles ; 9) Floating production, storage, and offloading facility (FPSO); 10) sub-sea completion and tie-back to host facility)

imagesCATTHQHA

Picture – Schematic of typical Gulf of Mexico offshore oil or gas platform (Courtesy of NOAA Fisheries)

Fixed platforms are built on concrete or steel legs, or both, anchored directly onto the seabed, supporting a deck with space for drilling rigs, production facilities and crew quarters. Fixed platforms are economically feasible for installation in water depths up to about 520 m (1,710 ft). Such platforms are, by virtue of their immobility, designed for very long term use (for instance the Hibernia platform). Various types of structure are used, steel jacket, concrete caisson, floating steel and even floating concrete.

Steel jackets are vertical sections made of tubular steel members, and are usually piled into the seabed.

A jacket is a steel substructure for an offshore installation. It is a complex construction, and designing one takes several months of engineering, 3D modelling, computations, design and method work.

Typical Arrangement of Jacket Structure:

  • Legs and braces
  • Jacket frame
  • Mudmat
  • Anode
  • Piles

Jacket_explained-infographics_6

Picture : “Jackets – a closer look” (Courtesy of KVAERNER)

Applicable Codes/ Standards:

STRUCTURAL

  • API RP-2A, 2B, 5B, AISC etc
  • AWS D1.1

CATHODIC PROTECTION

  • Applicable NACE, API, ASTM standards

JACKET AND APPURTENANCES CONSTRUCTION

Processes and Phases in Oil and Gas Fields Development EPCI Projects :

Processes and phases are two different aspects of project. A project may be divided into interdependent processes and into phases.

Project phases divide the project life cycle into manageable sections, sch as conception, development. Realization and termination.

Project processes (or Project Works) are those processes that are necessary for managing the project as well as those that are necessary to realize the project’s product.

Jacket Construction is a project processes/work of an oil and gas field development phase project.

Why ?

Question          : Why it is necessary to manage project processes within a quality management system?

Answer            : In order to achieve project objectives.

How to develop Project Management System for Jacket Construction ?

ISO9001:2008 International Standard promotes the adoption of a process approach when developing, implementing and improving the effectiveness of a quality management system, to enhance customer satisfaction by meeting customer requirements.

In addition, the methodology known as “Plan-Do-Check-Act” (PDCA) can be applied to all processes.

The project quality management system should be aligned, as far as is possible, with the quality management system of the originating organization (perennial quality management system).

For an organization to function effectively in executing Construction Works, it has to determine and manage numerous linked activities by establish, implement, document and maintain the Project Quality Management System, such as:

  • Project Manual / Project Quality Plan (PQP)
  • Onshore Construction Quality Control Plan (QCP)
  • Inspection and Test Plan (ITP)
  • Fabrication Procedures
  • Control Forms for Project
  • Quality Records

Project Quality Plan (PQP)

Document setting out the specific quality practices, resources and sequence of activities relevant to a particular Product, Project or CONTRACT.

Quality Control Plan (QCP)

An Onshore Construction Quality Control Plan (QCP) document setting out the specific quality practices, resources and sequence of activities relevant to Onshore Fabrication/Construction activities of a particular Project or CONTRACT.

PQP / QCP  is mainly for ensuring and monitoring that the fabrication is carried out as per contract specifications.

QCP outlines the Quality System for Construction/Fabrication, which will be followed by Contractor for the fabrication and load out of wellhead platforms infrastucture comprising of

  • Jackets,
  • Decks (Topsides),
  • Piles,
  • Conductors, and
  • Appurtenances
  • etc

for Oil and Gas FIELD DEVELOPMENT PROJECT in Onshore and Offshore.

Main activities in onshore Fabrication Yard are given as below:

  • Construction Project Management: includes Project HSE-Q Management Plan, resource managament, project schedule, project progress, document control center (DCC), etc.
  • Fabrication Engineering: design and development, to prepare shop drawing, welding plan / NDT map drawings, cutting plan, Piping support, E&I support drawings etc.
  • Procurement activities: purchasing, inspection, test, supply and delivery of materials and equipment.
  • Material Control (includes control of  Customer Property) : Receipt, acceptance, material identification, handling, storage, preservation, care and custody of procured items / Customer supplied items.
  • Material Logistics: follow up with Vendors for inspection , expediting delivery and shipping.
  • Pre-fabrication: Materials Preparation (Marking, Cutting, Profiling, Bending & Others)
  • Sub assemblies Manufacturing : Fit up and Welding
  • Calibration
  • QC Inspection: Visual/Dimensional Control & Inspection (to Check and record the dimensions of Products at different stages of Fabrication.), Wedling Inspection, NDE / DE
  • Final assemblies Manufacturing: Fit up and Welding
  • Post Welding : PWHT, where ever required.
  • Testing :  Hydrostatic Testing
  • Coating : Blasting, Painting/Insulation/Fire Proofing
  • Pre commissioning
  • Load out
  • Sea Fastening
  • Certification : Interfacing with Certifying Authority and Marine Warranty Surveyor
  • Quality Assurance : NCR control, CA/PA, Lesson learned, Customer Feedbacks/Complaints , Quality Audits, Project Quality System Manual/Procedures, Quality Records, QA Training and Awareness Program.
  • MDR / As Built Dossiers : Provision of final documentation as per Customer specifications.

Jacket Weighing

One of the most important process on jacket fabrication is Jacket Weighing. The weighing will be conducted at the structure final assembly location before the load-out when all components are being installed in proper position.

The objective of the weighing is to determine:

  • actual total weight of the structure
  • determine its plan location of the centre of gravity

Typical Project Documentation consists of:

  • Fabrication Procedure for the project
  • Shop drawings
  • Document Register
  • Project Schedule
  • QA/QC Procedures + Certificates (Personnel & Equipment as applicable)
  • HSE Procedures
  • WPS/PQR/WQT documents
  • Inspection & Test Plans for different disciplines
  • Inspection & Test Records (ITRs)
  • Material and Welding Traceability Records
  • Final Documentation refer to CONTRACT Specifications / Requirements.

Video: “Mumbai High North MNP Jacket” (Courtesy of  L&T Ltd and animation by Anthelion Technology )

We can see within the film,

  • Jacket ((8 Legged ~54 high) fabrication sequence
  • jacket and piles transfer from assembly area to jetty
  • jacket and piles load out onto cargo barge
  • sea fastening
  • towing / offshore transportation
  • offshore installation

Uploaded in YouTube by Anthelion Technology on 23 Apr 2013.

Description of video:

L&T offers a full range of facilities and equipment for oil & gas production, processing and transportation in association with world leaders. Engineering, Procurement and Construction solutions are offered to customers in India and abroad.

The film describes the Fabrication, Transportation and Installation of 13,500 MT MNP Jacket on which the MNP Platform rests. Its a part of the Mumbai High North Project undertaken by L&T Ltd (OGSP Division) for Oil and Natural Gas Corporation (ONGC).

Location: South Bassein Gas Field (North-West of Mumbai)

Anthelion Technology has shown in exact details, all the steps involved in the entire process. Such a presentation is a Visual Archive of complex engineering projects that engineering companies can develop for marketing, branding and media activities.

The video is a property of L&T Ltd and Anthelion Technology has developed this video. They have showcased it here only for presenting L&T skill set.

Related Links :

References / read more :

Advertisements

21 responses to “Jacket Construction of Oil & Gas Platform

  1. Pingback: akasse priser se hvad du sparer ved at skifte hurtigt·

  2. Pingback: url·

  3. Pingback: garcinia·

  4. Pingback: modern portrait photography·

  5. Pingback: awesome·

  6. Greetings! I stumbled this site on Yahoo. I am making this comment to find
    out which theme you are using on this site,
    I would love to have the theme that you’re
    using so I can use it on my website (pirater un compte facebook).

    Thank you!

  7. Hi! I came across this website on Twitter. I am posting here to know what theme you’re using on your blog,
    I would like to have the theme that you are using so I can put it
    on my blog (emulateur 3ds pour mac). Thanks.

  8. This is my first time pay a quick visit at here and i am
    truly impressed to read all at one place.

  9. I truly love your website.. Pleasant colors & theme.
    Did you build this web site yourself? Please reply back as I’m
    trying to create my very own website and would love
    to know where you got this from or what the theme is named.
    Thank you!

  10. Pingback: [EPCI Contractor for Oil & Gas Industry] Inspection and Test Status | Mande Blog·

  11. I blog frequently and I genuinely thank you for your information.
    This article has really peaked my interest. I’m going to take
    a note of your website and keep checking for new details about once a week.
    I subscribed to your RSS feed too.

  12. Hello Web Admin, I noticed that your On-Page SEO is is missing a few factors, for one you do not use all three H tags in your post, also I notice that you are not using bold or italics properly in your SEO optimization. On-Page SEO means more now than ever since the new Google update: Panda. No longer are backlinks and simply pinging or sending out a RSS feed the key to getting Google PageRank or Alexa Rankings, You now NEED On-Page SEO. So what is good On-Page SEO?First your keyword must appear in the title.Then it must appear in the URL.You have to optimize your keyword and make sure that it has a nice keyword density of 3-5% in your article with relevant LSI (Latent Semantic Indexing). Then you should spread all H1,H2,H3 tags in your article.Your Keyword should appear in your first paragraph and in the last sentence of the page. You should have relevant usage of Bold and italics of your keyword.There should be one internal link to a page on your blog and you should have one image with an alt tag that has your keyword….wait there’s even more Now what if i told you there was a simple WordPress plugin that does all the On-Page SEO, and automatically for you? That’s right AUTOMATICALLY, just watch this 4minute video for more information at. Seo Plugin

  13. My spouse and I stumbled over here from a different web address and thought I
    may as well check things out. I like what I see so now i’m following you.

    Look forward to looking into your web page yet again.

  14. I used to be looking on your website for a similar subject as the one, and am pleased to find out that yours is actually more than I expected for. Thanks, and in the event that you prefer you are able to have a look at my increased website here http://www.camllio.com/ and please allow me understand what you think about the outcome.

  15. Hello there! I could have sworn I’ve visited this blog before but after looking at a few of the articles I realized
    it’s new to me. Anyhow, I’m certainly delighted I stumbled upon it and
    I’ll be bookmarking it and checking back frequently!

  16. Hmm it seems like your site ate my first comment (it was extremely long)
    so I guess I’ll just sum it up what I had written and say, I’m thoroughly enjoying your blog.
    I as well am an aspiring blog writer but I’m still new to the whole thing.

    Do you have any suggestions for newbie blog writers?
    I’d certainly appreciate it.

  17. Moreover, a terrible credit standing may ensure it is impossible for you to obtain financing on everything Alexa Deichmann
    financial freedom is achievable to those
    that decide and decide to act on it.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s